September 10, 2018

Project Update – Twenty95 Manly

The development of Twenty95 Manly reached a significant milestone on 29th August 2018 with the completion of the first basement slab pour.

This level is Basement 4 of the car stacker for Twenty95 occupiers. The car stacker is designed to fit a total of 49 cars across the four basement levels.

Adjacent the car stacker, excavation and preparation works are ongoing at Basement 1 level. Screw piles have been installed in preparation for the residential lift shaft pit and footings for B1 slab as well as for the Tower Crane base.

The next major milestone on the project is the Tower Crane install which will help our Contractor speed up works onsite and see the project transform by bringing works out of the ground.

For those who are interested the final two remaining apartments each which three bedrooms are still available, location is amazing!

The project is on track to be completed in mid 2019.